Taft Avenue Sewer Improvement Project
Construction is active on the Taft Avenue Sewer Improvement Project. Beginning Thursday, May 1, crews will perform daytime paving work near the intersection of Taft Ave. and Glassell St.
Once paving is complete, re-striping will begin, followed by the installation of permanent K-rail along the median. This portion of work will occur at night, and will continue to help keep the project on schedule. After this work, the project will move into the next major phase: deep trenching work up to 20 feet below ground to install a larger, upgraded sewer line.
This page will be regularly updated with the latest project developments, schedules, and traffic impacts.
Paving Details
- Location: Taft Ave. near Glassell St.
- When: Thursday, May 1 – continuing for a few days
- Hours: Day work; 8:30 a.m.- 3:30 p.m.
- Impacts:
- Flaggers will be present during work hours.
- At least one lane will remain open for both eastbound and westbound traffic.
- Increased activity, dust, and noise are expected near the construction zone.
- Â
Construction Work
- Location:Â Taft Ave. from Glassell St. to Shaffer St.
- When: Currently ongoing – through the end of June. *
- Hours: Monday – Friday; 8:00 p.m. – 6:00 a.m.*
- Weekend work may be necessary. *
- Impacts:
- Permanent K-rail will remain for the duration of the work
- No U-turns allowed; some turns may be temporarily restricted – follow posted signs.
- At least one lane will remain open for eastbound and westbound traffic at all times.
- Parking will be restricted near the construction zone.
- Bus stops along Taft Ave. will be impacted during construction.
- Increased activity, dust and noise levels are expected near the construction zone.
- Traffic control measures will stay in place until each section of work is finished.
*All dates and times are subject to change due to operational factors or inclement weather.
Project Description:Â
The Taft Avenue Sewer Improvement Project will replace and relocate a portion of the Taft Sewer in the City of Orange.
This project will upsize almost two miles of pipe along Taft Avenue from Glassell Street to Sacramento Street, northbound on Sacramento Street to Brentford Avenue, to Breckenridge Street to Meats Avenue. The current pipe ranges between 12 to 15 inches and will be upsized to 18 to 21 inches.
A portion of the sewer that currently runs along Tustin Street will be relocated to North Sacramento Street where there is more room to install a larger pipe and facilitates the future maintenance of the pipeline.
Project Schedule: December 2024 – Fall 2026

Project Location
Stay In The Know
Community Liaison:
(714) 378-2965
Email:
constructionhotline@ocsan.gov
Sign up for text alerts:
click here
Signup for Email Notification
Site Location
Construction Schedule
2024 - 2026
Construction Budget
$20.4 million