This project has successfully installed four miles of regional sewer in the City of Anaheim and has connected this new pipe with a previously installed pipe in the City of Fullerton. Ongoing activities are as follows:
New Activity:
Final Street Paving on State College Blvd. Between Ball Rd. and 91 Freeway
Areas of State College Blvd. are ready for final paving! Paving will occur on the southbound side starting at Vermont Ave to Ball Rd, then proceed on the northbound side. As work is occurring, bus stops may be temporarily inaccessible. There will be lane reductions and occasional turn restrictions. See map for specifics.
- As early as May 27 thru June 4, 2021*
- Monday – Friday 6 a.m. – 6 p.m.
- No work on Memorial Day – May 31
Following the paving, crews will return to the area to adjust the manholes to an even surface level.
Miraloma Ave. and Miller St. Intersection
To support the recycling of water, a short segment of pipe needs to be installed to allow for flow to be redirected.
- As early as May 24 thru June 2021*
- Monday – Friday 8:30 a.m. – 3:30 p.m.
- K-rail (concrete barriers) will be installed to block off the work area.
- Travel lanes will be reduced. Left turn lanes in every direction will be restricted as the work is occurring.
- Left turns from westbound Miraloma Ave. to Miller St. will be restricted 24/7.
- See NOTICE for details.
Activity in Anaheim
State College Blvd. from Wagner Ave. to Lincoln Ave. – Detours
Travel lane reductions are necessary as crews work to restore State College Blvd. from Wagner Avenue to Lincoln Avenue. This will also require the intermittent closure of westbound Vermont Ave., Viking Ave., and Virginia Ave. to reach State College Blvd.
- Ongoing – June 2021*
- Monday – Friday, 7 a.m. – 5 p.m.
- Impacts: lane reductions, bus stops relocations (visit www.octa.net for details)
- Detour for Vermont and Viking. Detour for Virginia. Only one street will be closed at a time.
State College Blvd. and Romneya Intersection
Lateral connection work is resuming. This work is required to connect the local sewer to the regional sewer pipe.
- April 22, 2021 – June 2021*
- Monday – Friday, 8:30 a.m. – 3:30 p.m.
- Left turn restrictions
- Complete street restoration will be done in the summer
State College Blvd. and La Palma Ave. Intersection
Sewer installation is complete and lateral line connections to the local sewer line is anticipated to be completed by early June.
- Ongoing – June 2021*
- Monday – Friday 8:30 a.m. – 3:30 p.m.
- Left turn restrictions, U-Turns can be made at the next intersection
- Complete street restoration will be done in the summer
State College Blvd. and Center Street
Lateral line work in the intersection of State College Blvd. and Center St.
- Ongoing – May 2021 *
- Monday – Friday 7 a.m. – 5 p.m., occasional Saturdays
- Northbound traffic on State College Blvd. will be reduced to one lane. Southbound traffic will not be affected
- Access to State College Blvd. from Center St. will be restricted. Please use Underhill Ave. or Lincoln Ave.
- See NOTICE for details
Activity in Fullerton:
State College Blvd. and Orangethorpe Ave.
Sewer Line Connection – In 2017 three miles of sewer pipe was installed on State College Blvd. in the City of Fullerton. Now that the sewer has been installed in the City of Anaheim, we need to return to connect the two pipes. A small section of pipe will need to be installed to join the two pipes.
- Ongoing – mid-June 2021*
- Monday – Friday 7 a.m. – 7 p.m., occasional Saturdays
- Traffic may be reduced to one travel lane in each direction
- Northbound OCTA bus route will be temporarily relocated
- See NOTICE for details
- Complete street restoration will be done in the summer
Street Restoration: Ongoing through summer 2021. This includes paving and landscaping.
We encourage you to use alternate routes and allow extra time to reach your destination. For your safety and that of our crews, we ask that you obey reduced speed limit signs and traffic restrictions as these will change as work moves along State College Blvd.
We thank you for your continued patience as we work to improve Orange County’s infrastructure. To learn more about this project visit www.ocsan.gov/StateCollege.
*Dates are subject to change due to operational factors or inclement weather.
Project Description:
The project is replacing four miles of sewer along State College Boulevard from the SR-91 to Orangewood Avenue in the City of Anaheim. Construction began in late summer 2018 and is scheduled to be completed in spring 2021. Once the project is complete, eight million gallons of wastewater will be diverted to OC San’s Plant No. 1 in Fountain Valley for treatment before being sent to the Groundwater Replenishment System. This is Phase B of a two-phase project; Phase A was completed in 2017 and took place from Yorba Linda Blvd. to SR-91 in the City of Fullerton.