Huntington Beach Plant Future Construction

Home >> Construction >> Huntington Beach Plant Future Construction

OC San’s Treatment Plant No. 2 is located in Huntington Beach adjacent to the Santa Ana River and across the street from Huntington State Beach.

Sign up to receive the online OC San Connection Community Newsletter, focused on content regarding OC San programs, construction projects including those at OC San’s Plant No. 2, fun facts, and so much more.

FUTURE CONSTRUCTION PROJECT

HUNTINGTON BEACH (INCLUDES PLANT NO. 2)

  • Perimeter Wall Improvements (2025)
  • Digesters Rehabilitation (2025)
  • Activated Sludge Aeration Basin Rehabilitation (2027)
  • Digester Gas Facilities Replacement (2027)
  • Operations and Maintenance Complex (2027)

Perimeter Wall Improvements

Project Description:  This project will replace the perimeter chain link fence along the Talbert Marsh with a concrete wall. The top of the wall will have a wave-like pattern ranging between 8-feet to 11-feet tall.

Construction is anticipated to begin 2025 and take approximately 2 years to complete.

Digesters Rehabilitation at Plant No. 2

Project Description:  This project will rehabilitate existing Plant No. 2 digesters including repairing the digester domes, walls, and bridges, rehabilitating the hot water piping system, improving miscellaneous safety related items, and replacing electrical motor control centers that are obsolete.

Construction is anticipated to begin 2025 and take approximately 3 years to complete.

Activated Sludge Aeration Basin Rehabilitation at Plant No. 2

Project Description:  This project includes structural rehabilitation of the aeration basin’s reactor deck and adjacent concrete structures, coating the interior of reactor tanks to mitigate exposed concrete aggregate, replacement of all mechanical equipment, components, and piping, including all gates, valves, and appurtenances.

Construction is anticipated to begin 2027 and take approximately 3 years to complete.

Digester Gas Facilities Replacement

Project Description:  This project will replace the low- and high-pressure digester gas facilities at Plant Nos. 1 and 2 to meet current and future needs such as projected gas production and Air Quality Management District and National Fire Protection Association regulations.

Construction is anticipated to being 2027 and take approximately 5 years to complete.

Operations and Maintenance Complex

Project Description: This project will construct a new building for Operations, Maintenance, Collections and Construction Management staff.

Construction is anticipated to begin 2027 and take approximately 3 years to complete.

Project Map

Stay In The Know

Community Liaison:
(714) 378-2965

Email:
constructionhotline@ocsan.gov

Sign up for text alerts:
click here

Related Construction

Site Location