State College Sewer Construction Update – September 11, 2020
For more information please contact the Construction Hotline at (657) 208-7900 or via email at ConstructionHotline@ocsd.com
Pipe is being installed, sewer connections are being made, and we’re getting closer to having the four miles of sewer pipe in the ground. Crews continue to work in various areas to get things done as quickly as possible.
Don’t forget to check out an above the scenes view of our project.
Project Update:
E. South Street Detour – NEW ACTIVITY
A temporary detour restricting westbound traffic on E. South Street from State College Blvd. to Sunkist St. will be in place over the next month to connect the City of Anaheim local sewer to the newly installed OCSD regional sewer line. Only local traffic will be allowed on E. South Street.
- September 14, 2020 – October 2020*
- Monday – Saturday, 7 a.m. – 5 p.m.
- Detour route is in place to bypass the restricted area
- See NOTICE for details
Vermont Avenue to Virginia Avenue Â
Pipe installation in this area is now complete. Crews are continuing to work on constructing manholes that will be used later for future maintenance. The next step will be to connect the local sewer to new the sewer line.
- Ongoing – Fall 2020*
- Monday – Saturday, 7 a.m. to 3 a.m.
- Traffic impacts consist of lane reductions and left turn restrictions at Vermont and South Street. Only one travel lane will be allowed for northbound traffic. Sound blankets are installed to minimize noise and dust from the site.
- See NOTICE for details.
Virginia Avenue to Underhill Avenue
Installation of the final section of regional sewer pipe includes installation of a bypass system to reroute the sewer flow to maintain uninterrupted service. The installation also requires shoring of the trench. Longer workdays are required to complete the work as quickly as possible and minimize risk to the community.
- Ongoing – Fall 2020*
- Monday – Saturday, 7 a.m. to 3 a.m.
- Traffic impacts consist of lane reductions and left turn restrictions. Only one travel lane will be allowed for northbound traffic. Be aware that shoring may trigger minor vibration, which are closely monitored. Sound blankets are installed to minimize noise and dust from the site.
- See NOTICE for details.
Waterline Replacement: La Palma to Lincoln Avenue
A city of Anaheim waterline is being replaced concurrently with the sewer installation project to minimize impact to the community. The work will be done at night to prevent disruption to water service and to impact on the road as the sewer work occurs. Turn restrictions may occur intermittently.
- May 2020 – October 2020*
- Monday – Saturday, 5 p.m. – 3 a.m.
- See NOTICE  for details.
*Dates are subject to change due to operational factors or inclement weather.
Project Description:
The project is replacing four miles of sewer along State College Boulevard from the SR-91 to Orangewood Avenue in the City of Anaheim. Construction began in late summer 2018 and is scheduled to be completed in spring 2021. Once the project is complete, eight million gallons of wastewater will be diverted to OCSD’s Plant No. 1 in Fountain Valley for treatment before being sent to the Groundwater Replenishment System.  This is Phase B of a two-phase project; Phase A was completed in 2017 and took place from Yorba Linda Blvd. to SR-91 in the City of Fullerton.